Challenge
Solution
The use of prestressed, precast concrete I-girders with a conventional 225-mm-thick deck would not provide sufficient navigational clearance, so the superstructure for the new bridges will be comprised of 800-mm-deep prestressed, precast concrete box beams with a 150 mm concrete overlay. Also, the new bridge foundations utilize the abutments and pier caps as deep beams to span over the existing piled foundations of the Gardiner Expressway.




Learn more about how Entuitive approaches engineering challenges, and discover why Engineering Performance matters for your project.