Deloitte Tower

Montreal, Canada

The first privately funded commercial development built in downtown Montreal since the early 1990s, the 26-storey Deloitte Tower was completed in 2015.

Deloitte Tower

Montreal, Canada

The first privately funded commercial development built in downtown Montreal since the early 1990s, the 26-storey Deloitte Tower was completed in 2015.


Contact us to learn more about this project.

Get in Touch

Interested in learning about how we work? Message us and we will get back to you in a timely manner.

  • Your Contact Information
  • Write Message

Challenge
Structural elements must accommodate design choices, such as access floors, tight floor-to-floor heights, the Bush Shed structure, and a passenger drop-off area at street level.
Solution
The reinforced concrete structure incorporates a unique two-way slab band floor framing system. This economical design accommodates columns that slope through the height of the tower. Columns vary in strength from 60 MPa to 80 MPa and use 500 MPa reinforcement to reduce column size and increase the rentable floor area. Other sloped columns avoid the Bush Shed structure and a passenger drop off area at street level.

Learn more about how Entuitive approaches engineering challenges, and discover why Engineering Performance matters for your project.